Coconut Leather Shoes is a new company that has just started to produce shoes made from coconut leather. They have determined that it takes a new production line employee 180 minutes to produce a pair of shoes. It takes the same employee an average of 100 minutes to produce their 8th pair of shoes. The learning rate of Coconut Leather Shoes is 82.21%. What will the average time be for an employee to produce their second pair of shoes? (Make use of the exponential function and round your answer off to the second decimal)Group of answer choicesA. 147.97 minutesB. 140.00 minutesC. 121.64 minutesD. 157.50 minutes

Question

Coconut Leather Shoes is a new company that has just started to produce shoes made from coconut leather. They have determined that it takes a new production line employee 180 minutes to produce a pair of shoes. It takes the same employee an average of 100 minutes to produce their 8th pair of shoes. The learning rate of Coconut Leather Shoes is 82.21%. What will the average time be for an employee to produce their second pair of shoes? (Make use of the exponential function and round your answer off to the second decimal)Group of answer choicesA. 147.97 minutesB. 140.00 minutesC. 121.64 minutesD. 157.50 minutes

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The learning curve theory suggests that as a worker gains more experience, the time taken to complete a task decreases at a decreasing rate. This is often represented by an exponential function.

The learning rate of 82.21% means that each time the cumulative quantity of units produced doubles, the time per unit falls to 82.21% of its previous value.

In this case, the time taken to produce the first pair of shoes is 180 minutes. When the employee doubles their output (i.e., produces the second pair of shoes), the time per unit should fall to 82.21% of 180 minutes.

So, to calculate the average time for an employee to produce their second pair of shoes, we multiply the time taken to produce the first pair by the learning rate:

180 minutes * 0.8221 = 147.978 minutes

Rounding this to the second decimal place gives us 147.98 minutes.

So, the correct answer is A. 147.97 minutes.

This problem has been solved

Similar Questions

The time taken to produce the first unit of a product is 111 minutes. A learning curve of 88% can be applied with the production. Determine the time required (in minutes) to produce the 77th unit.

A library employee takes 45 seconds to process a returned item. One morning there were 30 items in the book return bin. How long did it take the employee to process all of the returned items? A. 22 ½ minutes B. 30 minutes C. 45 minutes D. 135 minutes E. 1350 minutes

Given the following information:Pairs of shoes expected to be produced 1,950,000Pairs of shoes produced 2,500,000Overhead rate $0.75What is the amount of applied overhead? $1,875,000 $412,500 $1,462,500 $550,000

The daily production level for a product is given by N(x)=120−120e−0.2x𝑁(𝑥)=120−120𝑒−0.2𝑥 units, where x is the time in hours after production begins. Find the average production during the first 77 hours.Enter your answer in exact form or rounded to the nearest whole number.

A café shop has a queue length, on average, of 10 customers and each customer has to wait 5 minutes to get their drinks from the time they enter the shop. How many customers are being served every hour?Group of answer choices120308040

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.