Which of the following is not a correct objective of the aggregate planning process? Maximise customer service Minimise changes in production rates Maximise utilisation of plant and equipment Maximise inventory investment
Question
Which of the following is not a correct objective of the aggregate planning process? Maximise customer service Minimise changes in production rates Maximise utilisation of plant and equipment Maximise inventory investment
Solution
The objective that is not correct for the aggregate planning process is "Maximise inventory investment".
Aggregate planning is a process used by operations management teams to balance production and demand in a way that minimises costs. The main objectives of aggregate planning include:
-
Maximising customer service: This involves ensuring that products are available when customers want them. This can involve holding some inventory, but the goal is to minimise the amount of inventory held while still meeting customer demand.
-
Minimising changes in production rates: Sudden changes in production rates can be costly. It's more efficient to produce at a steady rate.
-
Maximising utilisation of plant and equipment: This involves ensuring that the company's production facilities and equipment are used as efficiently as possible. This can help to minimise costs.
However, maximising inventory investment is not a correct objective. Holding large amounts of inventory can be costly due to storage costs, the risk of obsolescence, and the tying up of capital that could be used elsewhere. Therefore, the goal is usually to minimise inventory levels while still being able to meet customer demand.
Similar Questions
The objective of aggregate planning is usually to meet forecast demand while minimizing cost over the planning period TRUE False
An important difference in aggregate planning for services when compared to manufactured products is:Multiple ChoiceIt is much easier to hire and lay off workers for servicesCapacity is not limited by staffing level for servicesDemand is more predictable for servicesServices can't be inventoried
All of the following are steps in the general procedure for aggregate planning except:Multiple ChoiceIdentify pertinent company policies regarding labour.Convert the aggregate plan into a master production schedule.Determine capacities and production rates.Determine demand forecasts for each period.
Its purpose is to ensure that the organization's cost of operation is kept to the minimum over that period.Select one:a.Vendor selection planningb.Aggregate planningc.Human resource planningd.Sales planning
Mention the factors that need to be considered for aggregate planning. (30–100 words)