Sprint Retrospective is a Scrum event that has a timebox duration of three hours. (choose the BEST answer) Question 4 options: For a one-week Sprint, Sprint Retrospective's duration can be longer than three hours to get additional valuable feedback from the Scrum Team for future adaptation For a one-month Sprint, Sprint Retrospective's maximum duration is three hours For a one-week Sprint, Sprint Retrospective's maximum duration is three hours This is incorrect. Sprint Retrospective has a timebox duration of four hours For a one-month Sprint, Sprint Retrospective's duration is precisely three hours For a one-month Sprint, Sprint Retrospective's duration can be longer than three hours to get additional valuable feedback from the Scrum Team for future adaptation For a one-week Sprint, Sprint Retrospective's duration is precisely three hours

Question

Sprint Retrospective is a Scrum event that has a timebox duration of three hours.

(choose the BEST answer)

Question 4 options:

For a one-week Sprint, Sprint Retrospective's duration can be longer than three hours to get additional valuable feedback from the Scrum Team for future adaptation

For a one-month Sprint, Sprint Retrospective's maximum duration is three hours

For a one-week Sprint, Sprint Retrospective's maximum duration is three hours

This is incorrect. Sprint Retrospective has a timebox duration of four hours

For a one-month Sprint, Sprint Retrospective's duration is precisely three hours

For a one-month Sprint, Sprint Retrospective's duration can be longer than three hours to get additional valuable feedback from the Scrum Team for future adaptation

For a one-week Sprint, Sprint Retrospective's duration is precisely three hours

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution 1

The best answer is: "For a one-month Sprint, Sprint Retrospective's maximum duration is three hours".

This is because, according to the Scrum Guide, the Sprint Retrospective is an event in Scrum that is time-boxed to three hours for a one-month Sprint. For Sprints less than one month, the event is usually shorter. Therefore, for a one-week Sprint, the Sprint Retrospective would not be three hours long, it would be shorter.

This problem has been solved

Solution 2

The best answer is: "For a one-month Sprint, Sprint Retrospective's maximum duration is three hours".

This is because, according to the Scrum Guide, the Sprint Retrospective is an event in Scrum that is time-boxed to three hours for a one-month Sprint. For Sprints less than one month, the event is usually shorter. Therefore, for a one-week Sprint, the Sprint Retrospective would not be three hours long, it would be shorter.

This problem has been solved

Similar Questions

The time box for the Sprint Planning event is?8 hours for a monthly sprint. For shorter sprints, it is usually shorter4 hoursWhenever it is doneMonthly

Question 3How long is a typical Sprint’s timebox?1 pointBetween one and three daysBetween one and four weeksBetween two and three months

What is the purpose of the Sprint Retrospective?To identify major items that went wellTo combine the learnings from the last SprintTo create a plan for implementing improvementsTo increase product qualit

Which of the following factors should you consider when setting the length of a Sprint’s timebox? Select all that apply.1 pointThe likelihood that the project will go over budgetHow much overhead—such as testing and review—goes into the delivery of the productThe expected frequency of changesHow much focused time the solution Developers need to build a Backlog item

When do design sprint retrospectives usually take place?1 pointA couple weeks before a design sprint During a design sprintImmediately after a design sprintA few weeks after the design sprint

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.