Stuart completed a piece of work alone in 16 days. What fraction of work was completed by him in 6 days?  Ops:   A. 5/8    B. 3/8    C. 3/4    D. 3/5

Question

Stuart completed a piece of work alone in 16 days. What fraction of work was completed by him in 6 days?  Ops:   A. 5/8    B. 3/8    C. 3/4    D. 3/5

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we need to understand that the amount of work Stuart completes each day is constant.

Step 1: We know that Stuart completes 1 whole piece of work in 16 days. So, the fraction of work he completes each day is 1/16.

Step 2: To find out how much work he completes in 6 days, we multiply the fraction of work he completes each day by 6.

So, 1/16 * 6 = 6/16 = 3/8.

Therefore, Stuart completes 3/8 of the work in 6 days. So, the answer is B. 3/8.

This problem has been solved

Similar Questions

The Simple Interest on $768 for 5 years at 20% p.a. is: Ops: A. $688 B. $768 C. $828 D. $728 Q 12. Stuart completed a piece of work alone in 16 days. What fraction of work was completed by him in 6 days? Ops: A. 3/5 B. 3/4 C. 3/8 D. 5/8

Select the correct answerA and B can do a piece of work in 6 days and 8 days, respectively. With the help of C, they completed the work in 3 days and earned Rs.1,848. What was the share of C?OptionsRs.924Rs.462Rs.231Rs.693

Select the correct answerA can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options3 days5 days2.5 days1.5 days

Twelve children take sixteen days to complete a work which can be completed by eight adults in twelve days. Sixteen adults started working and after three days ten adults left and four children joined them. How many days will they take to complete the remaining work ? 3 b. 4 c. 6 d. 8 e. none of these

Select the correct answerTo do a certain work, the ratio of efficiency of A to that of B is 3 : 7. Working together, they can complete the work in 10.5days. They work together for 8 days. 60% of the remaining work will be completed by A alone in?Options5.5days6.5 days5 days4 days

1/3