A project is to build four walls in four days and the budget at completion is 1000 dollars.At the end of the third day.you have completed 3 walls and spent $1000.What is your cost variance? $500 0-$500 ○-$250 ○$0

Question

A project is to build four walls in four days and the budget at completion is 1000 dollars.At the end of the third day.you have completed 3 walls and spent 1000.Whatisyourcostvariance?1000.What is your cost variance? 500 0-500500 ○-250 ○$0

🧐 Not the exact question you are looking for?Go ask a question

Solution

To calculate the cost variance, we first need to understand what it is. Cost variance (CV) is a measure of cost performance on a project. It is equal to the earned value (EV) minus the actual cost (AC).

Here's how to calculate it:

  1. Calculate the Earned Value (EV): EV is the value of the work actually completed. Since the total budget is 1000for4walls,thebudgetforeachwallis1000 for 4 walls, the budget for each wall is 250 (1000/4). Since 3 walls have been completed, the EV is 3 * 250=250 = 750.

  2. Identify the Actual Cost (AC): AC is the actual cost incurred for the work completed. In this case, it's given as $1000.

  3. Calculate the Cost Variance (CV): CV = EV - AC. So, CV = 750750 - 1000 = -$250.

So, the cost variance is -$250.

This problem has been solved

Similar Questions

A planning budget called for 500 units to be produced and total direct labor cost of $7,500. Actual production was 600 units and actual direct labor cost was $9,300. The spending variance is Blank______.Multiple choice question.$300 F$1,800 U$300 U$1,500 F$1,500 U

XYZ Company makes one product and has calculated the following amounts for direct labor: AH x AR = $84,000; AH x SR = $83,000; SH x SR = $85,000. Compute the direct labor cost variance.Multiple choice question.$2,000 F$1,000 U$2,000 U$1,000 F

A job was budgeted to require 4 hours of labor per unit at $11.00 per hour. The job consisted of 7,000 units and was completed in 24,000 hours at a total labor cost of $312,900. What is the direct labor rate variance?

Given the following information, calculate the materials price variance:Direct material purchased and used 30,000 kgCost of direct material $84,000Unfavourable direct materials usage variance $3,000Standard quantity of direct materials allowed for May production 29,000kg

XYZ Company makes one product and has calculated the following amounts for direct materials: Actual cost: AQ x AP = $150,000; AQ x SP = $145,000; Standard cost: SQ x SP = $152,000. Compute the direct materials variance.Multiple choice question.$7,000 F$2,000 F$5,000 U$2,000 U

1/2

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.