Which of the following does not constitute the role of a project manager? Integrator and coordinator  Business case approval  Project delivery  Project planning and controlling

Question

Which of the following does not constitute the role of a project manager? Integrator and coordinator  Business case approval  Project delivery  Project planning and controlling

🧐 Not the exact question you are looking for?Go ask a question

Solution

The role that does not constitute the role of a project manager is "Business case approval". This is typically a role for stakeholders or senior management, not the project manager. The project manager is responsible for integrating and coordinating the project, delivering the project, and planning and controlling the project. However, the approval of the business case, which is the justification for the project, is usually done by those who are funding the project or have a major stake in its outcome.

This problem has been solved

Similar Questions

Does the role of the Project Manager differ from project to project?

What is the role of the Project Manager? The Project Manager has many responsibilities. The role of the project manager aligns with the Project Management Process Groups. From the list below, please select the Project Management Process Groups

Which of the following responsibilities typically belong to the project manager? Select all that apply.1 pointDevelop the project management planSign off on the budgetControl change and monitor project qualityDirect project work and report on progress to stakeholders

The role of the project manager includes managing the team members, developing the project plan, assigning resources and serving as the primary point of contact for people outside the project team.True or False?Select one:TrueFalse

Select all that applyWith respect to the roles and responsibilities of a project manager, which of the following are true?Multiple select question.Project manager are not responsible for making any necessary adjustments to the schedule along the way.Project manager are responsible for monitoring results against plans.Project manager are responsible for taking corrective action when necessary.Project manager are not responsible for making any changes in a plan.Project manager are responsible for formulating plans and objectives.

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.