Which from the following represents the correct project cycle? ans. Planning→ Initiating→ Executing→ Closing Initiating→ Executing→ Planning→ Closing Planning→ Executing→ Initiating→ Closing Initiating→ Planning→ Executing→ Closing

Question

Which from the following represents the correct project cycle? ans. Planning→ Initiating→ Executing→ Closing

Initiating→ Executing→ Planning→ Closing

Planning→ Executing→ Initiating→ Closing

Initiating→ Planning→ Executing→ Closing

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct project cycle is: Initiating→ Planning→ Executing→ Closing. This is the standard order of phases in project management according to the Project Management Institute (PMI).

  1. Initiating: This is the first phase where the project is defined at a broad level. It involves identifying the project's stakeholders, defining the project objectives, and preparing a project charter.

  2. Planning: In this phase, detailed planning is done which includes defining the project scope, developing the project schedule, planning the budget, and setting up the project management plan.

  3. Executing: This is the phase where the actual work is done. The project team works on the tasks defined in the project plan and produces the deliverables.

  4. Closing: This is the final phase where the project is formally closed. It involves handing over the deliverables, releasing the project resources, and evaluating the project's success or failure.

This problem has been solved

Similar Questions

Choose the correct sequence of various phases of a project life cycle?/किसी परियोजना जीवन चक्र के विभिन्न चरणों का सही क्रम चुनें Planning, Initiation, Monitoring/Control, Execution, Closure/योजना, आरंभ, निगरानी/नियंत्रण, निष्पादन, समापन Initiation, Planning, Monitoring/Control, Execution, Closure/आरंभ, योजना, निगरानी/नियंत्रण, निष्पादन, समापन Planning, Initiation, Execution, Monitoring/Control, Closure/योजना, आरंभ, निष्पादन, निगरानी/नियंत्रण, समापन Initiation, Planning, Execution, Monitoring/Control, Closure/आरंभ, योजना, निष्पादन, निगरानी/नियंत्रण, समापन

The project ______________ is the first stage of a project cycleQuestion 7Answera.Evaluation stageb.Idea stagec.Execution staged.Selection stage

Which of the following is not correct related to a "Plan"?Choices:- Any diagram List of steps Details of timing Must never have details of resources

In which of the following project phases is the project schedule developed?a.Designb.Conceptualc.Implementationd.Planning

Which of the following components of a project plan is completed first? Work breakdown structureRisk management planProject budgetProject schedule

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.