Multiple Choice QuestionA major goal of progress reporting is to catch any negative variances from plan as early as possible to determine if corrective action is necessary. The project network schedule, derived from the ______, serves as the baseline to compare against actual performance.Multiple choice question.project management information system (PMIS)baseline Gantt chartsproject sponsor’s targetswork breakdown structure (WBS)/organization breakdown structure (OBS)analogous project estimates from previous projects
Question
Multiple Choice QuestionA major goal of progress reporting is to catch any negative variances from plan as early as possible to determine if corrective action is necessary. The project network schedule, derived from the ______, serves as the baseline to compare against actual performance.Multiple choice question.project management information system (PMIS)baseline Gantt chartsproject sponsor’s targetswork breakdown structure (WBS)/organization breakdown structure (OBS)analogous project estimates from previous projects
Solution
The correct answer is "work breakdown structure (WBS)/organization breakdown structure (OBS)".
Here's why:
The project network schedule is derived from the work breakdown structure (WBS) and the organization breakdown structure (OBS). The WBS breaks down the project into smaller, manageable tasks, while the OBS identifies the organizational units responsible for each task. This serves as the baseline to compare against actual performance.
The other options are not correct because:
- The project management information system (PMIS) is a tool that provides project managers with the ability to organize and manage the project's information.
- Baseline Gantt charts are used to represent the project schedule and track its progress, but they are not used to derive the project network schedule.
- The project sponsor’s targets are the goals set for the project, but they do not serve as the baseline for the project network schedule.
- Analogous project estimates from previous projects can be used to inform the project schedule, but they are not used to derive the project network schedule.
Similar Questions
What is the major goal of progress reporting?Multiple choice question.To determine whether corrective action is necessaryTo determine authority over the projectTo determine what data to collect
The network diagram chart is the most favored, used, and understandable option for reporting project progress to upper management.True false question.TrueFalse
Project progress reports are designed and communicated in:Multiple choice question.written or oral form.person.written form only.
Multiple Choice QuestionAlthough different stakeholders need different levels of detail, most project progress reports include ___.Multiple choice question.current status of project schedulecurrent status of project conflictsteam member performance reports
Project managers use a Blank______ to keep distal stakeholders informed of project progress.Multiple choice question.detailed accounting of project progressschedule of major project milestonesnetwork diagramcontrol chart
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.