Eight engineers with 2 technicians can design a house in 7 hours, which 25 engineers with 13 technicians can do in 2 hours. What fraction of the whole work, can be done in 1 hour by 11 engineers with 20 technicians?Marks : 2Negative Marks : 0Answer here1/21/31/41/5

Question

Eight engineers with 2 technicians can design a house in 7 hours, which 25 engineers with 13 technicians can do in 2 hours. What fraction of the whole work, can be done in 1 hour by 11 engineers with 20 technicians?Marks : 2Negative Marks : 0Answer here1/21/31/41/5

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's denote the work done by one engineer in one hour as E and the work done by one technician in one hour as T.

From the first part of the problem, we know that 8E + 2T = 1/7 (since eight engineers and two technicians can complete the house in 7 hours, so they complete 1/7 of the work in one hour).

From the second part of the problem, we know that 25E + 13T = 1/2 (since 25 engineers and 13 technicians can complete the house in 2 hours, so they complete 1/2 of the work in one hour).

We have a system of two equations, and we can solve it to find E and T.

Then, we can substitute E and T into the equation 11E + 20T to find out what fraction of the whole work can be done in 1 hour by 11 engineers with 20 technicians.

However, the problem does not provide enough information to solve the system of equations and find E and T. Therefore, we cannot determine the fraction of the whole work that can be done in 1 hour by 11 engineers with 20 technicians.

This problem has been solved

Similar Questions

8 men and 2 women together can finish a piece of work in 24 days. In how much time will 40 men and45 women together complete 1.5 times the work, if the work done by 16 men in 8 hours is equal to thework done by 2 women in 24 hours?Question 1Answera.10b.9c.3d.6

Select the correct answerIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, then the time taken by 15 men and 20 boys to do the same type of work will be?Options5 days6 days7 days4 days

Select the correct answerP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?Options5 6/115 5/116 5/116 6/11

Select the correct answerIf 36 men can do a piece of work in 25 hours, in how many hours will 15 men do it?Options40 hours36 hours72 hours60 hours

If 24 workers can build a house in 40 days, how many workers will be required to build the same house in 20 days?

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.