How much concrete is needed to fill a section of sidewalk that is 120 inches long, 72 inches wide, and 6 inches high?
Question
How much concrete is needed to fill a section of sidewalk that is 120 inches long, 72 inches wide, and 6 inches high?
Solution
To determine the amount of concrete needed to fill the section of the sidewalk, we need to calculate the volume of the rectangular prism formed by the given dimensions.
-
Identify the dimensions:
- Length (L) = 120 inches
- Width (W) = 72 inches
- Height (H) = 6 inches
-
Use the formula for the volume of a rectangular prism:
-
Substitute the given dimensions into the formula:
-
Perform the multiplication:
Therefore, the amount of concrete needed to fill the section of the sidewalk is 51,840 cubic inches.
Similar Questions
Jeremy is pouring a rectangular concrete pad for a driveway. It measures 9 yd by 24 ft and he wants 6 inches of concrete.How many cubic yards of concrete should Jeremy order (to nearest whole number)?
Pat is pouring a rectangular concrete pad for a driveway. It measures 11 yd by 24 ft and he wants 7 inches of concrete.How many cubic yards of concrete should Pat order? Answer to the nearest HUNDREDTH.
A concrete piece requires 37.7 cubic meters (m3) of concrete. Use the fact that 1 yard is approximately equal to 0.9144 m to convert this volume to cubic yards (yd3). Round your answer to the nearest hundredth. Do not type the units in the space below.
What is the area of a driveway that is 31 feet long, 18 feet wide, and 8 inches high?
How much dirt is needed to fill a rectangular flower box that is 24 inches long, 12 inches wide, and 10 inches high?