The Scrum Master needs to make sure the team is able to get tasks done on time. How can they achieve this? Select all that apply.1 pointThey can help remove blockersThey can add in iterationsThey can prioritize issues from usersThey can pick up developer tasks
Question
The Scrum Master needs to make sure the team is able to get tasks done on time. How can they achieve this? Select all that apply.1 pointThey can help remove blockersThey can add in iterationsThey can prioritize issues from usersThey can pick up developer tasks
Solution
The Scrum Master can help the team get tasks done on time by:
-
Helping remove blockers: This is one of the primary responsibilities of a Scrum Master. Blockers are issues that prevent the team from moving forward with their tasks. The Scrum Master can work to identify these issues and find solutions to remove them.
-
Adding in iterations: While this is not a direct responsibility of the Scrum Master, they can suggest adding iterations if they see that the team is struggling to complete tasks within the current sprint. This would allow for more time to complete tasks, but it should be a last resort as it can disrupt the project timeline.
-
Prioritizing issues from users: This is typically a product owner responsibility, but a Scrum Master can assist in this process. By helping to prioritize user issues, the team can focus on the most critical tasks first, which can help ensure they are completed on time.
-
Picking up developer tasks: This is generally not a recommended practice. The Scrum Master's role is to facilitate and remove obstacles for the team, not to take on development tasks. Doing so could distract from their primary responsibilities and potentially slow down the team's progress.
Similar Questions
Imagine you are the Scrum Master launching the first phase of services for a company project. Your team takes a long time to finish tasks and, as a result, they are a month behind schedule. How can you diagnose the problem and help your team hit their targets? Select all that apply.1 pointReplace slower team members with more efficient ones.Use Retrospectives to discover opportunities to improve how the team is working.Run more demos of solutions with the team to identify areas for improvement.Prioritize the right user stories and focus on only a few per Sprint.
Question 3What is the role of the Scrum master?1 pointDetermines priorities, requirements, and when to shipExercises management authority over the teamAssigns each item in the sprint plan to someone on the teamCoaches the team and shields them from external interference
Question 6In Scrum, who determines priorities and how work is accomplished?1 pointThe scrum team negotiates commitments with the product owner and has authority on how to reach commitments.The scrum master reprioritizes the backlog and directs the team.The customer determines priorities and how the work is carried out.The project owner directs how and when work will be done, and which team members will do it.
Question 4Which answer describes the Scrum team?1 pointThe Scrum master develops a plan and the team works according to it.The team pulls work off the plan, assigns it to themselves, and develops software.Members work on projects according to their assigned roles.Members come on and off the team as needed, each contributing as needed.
What is the main responsibility of the Scrum Master?To coach the teamTo make sure all 3 questions are answered during the daily scrumTo act as a Project ManagerTo promote and support Scrum as defined in the Scrum guide
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.