A and B undertook to do a piece of work for Rs.4800.A alone could do it in 8days and B alone in 12days.With the assistance of C they finished the work in 4days.Then B’s share of the money is*1 point1.22502.16003.7504.1500

Question

A and B undertook to do a piece of work for Rs.4800.A alone could do it in 8days and B alone in 12days.With the assistance of C they finished the work in 4days.Then B’s share of the money is*1 point1.22502.16003.7504.1500

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we first need to find the rates at which A, B, and C work.

  1. A can complete the work in 8 days, so A's work rate is 1/8 of the work per day.
  2. B can complete the work in 12 days, so B's work rate is 1/12 of the work per day.

Given that A, B, and C together can complete the work in 4 days, their combined work rate is 1/4 of the work per day.

We can find C's work rate by subtracting A and B's work rates from the combined work rate:

C's work rate = (1/4) - (1/8 + 1/12) = 1/4 - 5/24 = 1/24 of the work per day.

Now, we need to find out how much work B did. B worked for 4 days at a rate of 1/12 of the work per day, so B did (4 * 1/12) = 1/3 of the work.

The total payment for the work is Rs.4800, so B's share of the money is (1/3) * Rs.4800 = Rs.1600.

So, the answer is 2.1600.

This problem has been solved

Similar Questions

A, B and C, each of them working alone can complete a job in 4, 6 and 8 days respectively. If all three of them work together to complete a job and earn Rs. 1170, then what will be B’s share in the total earnings?

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

Select the correct answerIf A had worked alone he would have taken 63 hours to do the task. What is B’s share, if A and B together on a task finishing it in 36 hours and they get paid Rs.5,950 for it?Options3600340025502750

Select the correct answerThe labourers A, B, C were given a contract of Rs.750 for doing a certain piece of work. All the three together can finish the work in 8 days. A and C together can do it in 12 days, while A and B together can do it in 13 1/3 days. The money will be divided in the ratio?Options4 : 7 : 54 : 5 : 65 : 7 : 45 : 6 : 8

A and B entered in to a partnership with investments of Rs. 15000 and Rs. 40000 respectively. After 3 months A left from the business, at the same time C joins with Rs. 30000, At the end of 9 months they got Rs. 7800 as profit. Find the share of B?OptionsRs. 4800Rs. 7400Rs. 1720Rs. 6000

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.