To identify project tasks for your project plan, you review project documentation and research your project online. You have connected with members of your project team and other experts in your organization to examine your list of tasks. You decide you need additional details about a key deliverable. Who should you speak to in order to receive the missing information?1 pointYour most senior stakeholderOne of your high-influence stakeholdersYour company’s most senior project managerYour company’s Chief Operating Officer
Question
To identify project tasks for your project plan, you review project documentation and research your project online. You have connected with members of your project team and other experts in your organization to examine your list of tasks. You decide you need additional details about a key deliverable. Who should you speak to in order to receive the missing information?1 pointYour most senior stakeholderOne of your high-influence stakeholdersYour company’s most senior project managerYour company’s Chief Operating Officer
Solution
To identify project tasks for your project plan, you review project documentation and research your project online. You have connected with members of your project team and other experts in your organization to examine your list of tasks. You decide you need additional details about a key deliverable. Who should you speak to in order to receive the missing information?
Based on the given information, the most appropriate person to speak to in order to receive the missing information about the key deliverable would be one of your high-influence stakeholders. These stakeholders are individuals who have a significant impact on the project and possess the necessary knowledge and expertise to provide the required details. By engaging with a high-influence stakeholder, you can gather the missing information and ensure the successful completion of the project.
Similar Questions
You have gathered information from project documentation and the project team. With this information, you identified and created a list of tasks for your project plan. What is the next step for completing your project plan?1 pointIdentify the order in which tasks need to be completed. Identify points in the project plan where you can evaluate completed work.Identify tasks that carry a high risk.Identify tasks that stakeholders have a particular interest in.
As a project manager working on a new project, you need to identify potential tasks for the team. For this project, you plan to get input from the team’s leadership about tasks. Which type of interaction would be best to identify tasks?1 pointOne-on-one conversations with team membersMeeting with key stakeholdersConsult with experts not on the teamGroup brainstorm with the team
As a project manager working on a new project, you need to identify potential tasks for the team. For this project, there are many roles that require specific expertise and many distinct tasks. Additionally, some team members will have similar tasks. You’d like to have the team generate a full list of detailed tasks and get agreement on the tasks and owners. What interaction should you have?1 pointGroup brainstorm with the teamLeadership check-in with key stakeholders Discussion with experts not on the teamOne-on-one conversations with team members
8. You are the project manager for a project with 200 stakeholders. The team identified five individuals as key stakeholders. You are developing the stakeholder engagement plan, which is an actionable blueprint of how to interact with the stakeholders to support the project objectives. You will base the actions taken on an analysis of key stakeholder needs, their level of interest, and their potential impact on project success. Where will you find this information to analyze? A. Project charter B. Project management plan C. Files located in the human resource department D. Stakeholder register
You communicate a project problem to a key stakeholder. What question should you ask yourself to ensure the information you provide is necessary?1 pointDoes this information help the stakeholder make a decision easily?Does this information give all the details of the problem to the stakeholder?Does this information link to important project documentation?Does this information provide the stakeholder extra context about the problem and project?2.Question 2