The load forecasting of DiscoZ on 10 May 2023 is equal to 400MW. However, on that day the actual demand is equal to 432MW. In a balancing market, the selling price is RM0.40/MW while its purchasing price is RM 0.20/MW. Calculate the cost DiscoZ needs to pay to the balancing market.
Question
The load forecasting of DiscoZ on 10 May 2023 is equal to 400MW. However, on that day the actual demand is equal to 432MW. In a balancing market, the selling price is RM0.40/MW while its purchasing price is RM 0.20/MW. Calculate the cost DiscoZ needs to pay to the balancing market.
Solution
To calculate the cost DiscoZ needs to pay to the balancing market, we first need to determine the difference between the forecasted demand and the actual demand.
The forecasted demand is 400MW and the actual demand is 432MW.
So, the difference is 432MW - 400MW = 32MW.
This means DiscoZ needs to purchase an additional 32MW from the balancing market to meet the actual demand.
The purchasing price in the balancing market is RM 0.20/MW.
Therefore, the cost DiscoZ needs to pay to the balancing market is 32MW * RM 0.20/MW = RM 6.40.
Similar Questions
Predicted demand of a product for the current month = 4,064 unitsActual demand of the product for the current month = 4,806 unitsSmoothing constant = 0.2Required: Forecast the demand of the product (in units) for the next month?
In a bilateral market model, how much power is needed to buy/sell from the power exchange company if the forecasting and actual demands are 350MW and 300MW, respectively
Consider an electricity market where the base of the demand curve is vertical and varieslinearly between 4000MW and 8000MW (so is equally likely to be found anywhere inthat range). Above 7500MW demand can be curtailed at a price of $4000/MWh. Themarket is competitive with three types of plants as below.Technology FC per MWh Variable costs perMWhCarbon Emissionsin tonnes perMWhPeak (diesel peaker) $18 $160 25Mid (gas) $35 $50 10Baseload (hydro) $55 $0 0(a)What is the optimal amount of baseload plant that should be built? (2 marks)(b) What is the duration of the price spike so that the peaker plant just recovers itsfixed costs? (2 marks)(c) What is the optimum mid-load capacity? (2 marks)(d) What is the total capacity and hence peak capacity? (2 marks)(e) Sketch the load duration curve and the offer stack (2 marks)(f) Show all plants just cover costs (4 marks)(g) Suppose now the government imposes a tax of $30 a tonne. Suppose there is nochange in capacity (so capacity doesn’t adjust). Calculate the profit that each type ofplant makes. Why do some plants make a profit even though the market iscompetitive? (4 marks)
Company DIB observes the demand of product Z over 20 periods as follow:Period ActualDemand (units)Period ActualDemand (units)1 198 11 2002 175 12 1983 172 13 1954 194 14 2235 177 15 2026 186 16 1847 193 17 1678 196 18 1949 211 19 17010 205 20 159Assume the initial forecast is 200 units.Requirements:a) Plot a line chart* that covers 20 periods and consists of the following THREE (3) lines:The actual demand line (5 marks)The exponential smoothing forecast line with alpha = 0.2 (5 marks)The exponential smoothing forecast line with alpha = 0.8 (5 marks)*Suggestion: Use MS Excel to plot the line chart.b) Compute the Mean Absolute Deviation (MAD) for periods 1 to 20. Tabulate youranswers. (11 marks)c) Which smoothing constant produces a better forecast? Comment on your observation.(4 marks)Note: Keep your answers to ONE (1) decimal place.
Manico Company produces three products-X, Y, & Z-with the following characteristics: XYZSelling price per unit$21.00$17.00$16.00Variable cost per unit12.6012.756.40Contribution margin per unit$ 8.40$4.25$9.60 === ======= ====== ====Machine hours per unit536The company has only 2,000 machine hours available each month. If demand exceeds the company's capacity, in what sequence should orders be filled if the company wants to maximize its total contribution margin? Question 19Answera.Orders for Y first, X second, and Z thirdb.Orders for X first, Z second, and Y thirdc.Orders for Z first, X second, and Y thirdd.Orders for Z first and no orders for X or Y
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.