Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse
Question
Using the time-cost CPM model, crashing is used to improve the project quality.Group of answer choicesTrueFalse
Solution
False
Crashing in the time-cost CPM (Critical Path Method) model is not used to improve project quality. Instead, it is a technique used to shorten the schedule duration for the least incremental cost by adding resources. Crashing only reduces the time it takes to complete the project but does not necessarily improve the quality of the project. Quality of a project is dependent on factors like adherence to standards, performance, reliability etc., not just the time it takes to complete it.
Similar Questions
What method can be used to shorten the project completion time by reducing the completion time of one or more critical activities at a cost?Group of answer choiceslinear regressionproject revvingproject crashingproject factoring.
CPM is suitable for which kind of projects?a.Micro projectsb.Large projectsc.Mini projectsd.Micro and Mini projects
Crashing of project activities will not change the critical path in the project network.Group of answer choicesTrueFalse
What is the number one cause of Project/Program Failure?
What are some reasons project scheduling is not done well?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.