Fill in the Blank QuestionFill in the blank question.JP Service Company has budgeted direct labor hours of 100 and direct labor cost per hour of $25 for data analysis personnel and budgeted direct labor hours of 50 and direct labor cost per hour of $30 for staff accountants. JP Service Company's cost of direct labor is $_?
Question
Fill in the Blank QuestionFill in the blank question.JP Service Company has budgeted direct labor hours of 100 and direct labor cost per hour of 30 for staff accountants. JP Service Company's cost of direct labor is $_?
Solution
To calculate the total cost of direct labor for JP Service Company, you need to multiply the number of budgeted direct labor hours by the direct labor cost per hour for each type of personnel.
First, calculate the cost for data analysis personnel: 100 hours * 2500
Next, calculate the cost for staff accountants: 50 hours * 1500
Finally, add these two amounts together to get the total cost of direct labor: 1500 (accountants) = $4000
So, JP Service Company's cost of direct labor is $4000.
Similar Questions
Multiple Choice QuestionThe formula to compute the budgeted direct labor cost for a service firm is:Multiple choice question.budgeted total labor cost divided by total direct labor cost per hourbudgeted direct labor cost times direct labor cost per hourbudgeted direct labor hours times direct labor cost per hourbudgeted labor hours times labor cost per hour
Fill in the Blank QuestionFill in the blank question.A manufacturing company has budgeted direct labor hours of 940 at a budgeted direct labor hour rate of $15. The budgeted fixed cost is $950 per month. The total budgeted overhead cost for this month will be $_.
Multiple Choice QuestionLanden Company uses a single plantwide overhead rate based on direct labor hours. Total budgeted overhead costs are $200,000. Total budgeted direct materials are $50,000 and total budgeted direct labor hours are 80,000. What is the plantwide overhead rate per direct labor hour?Multiple choice question.$2.50$4.00$0.40$0.25
The formula to compute the budgeted direct labor cost isMultiple choice question.units to produce times direct labor required per unit plus direct labor cost per hourunits to produce times direct labor required per unit times direct labor cost per hourunits to produce times direct labor required per unit divided by direct labor cost per hourunits to produce divided by direct labor required per unit times direct labor cost per hour
During the month of July, direct labor cost totaled $12,000 and direct labor cost was 30% of prime cost. If total manufacturing costs during July were $86,000, the manufacturing overhead was_______?