Which type of project cost estimate is the most accurate?a.Order of magnitudeb.Preliminaryc.Conceptuald.Definitive

Question

Which type of project cost estimate is the most accurate?a.Order of magnitudeb.Preliminaryc.Conceptuald.Definitive

🧐 Not the exact question you are looking for?Go ask a question

Solution

The most accurate type of project cost estimate is d. Definitive. This type of estimate is usually performed when all the project details are clear and well-defined. It provides the highest level of accuracy, often with a range of -5% to +10% variance.

Similar Questions

Name three basic tools and techniques used for project cost estimatio

These are part of the Techniques for Estimating Project Costs, except:*A. Three-Point EstimationB. Analogous EstimationC. Direct Labor Expense

15. You and several of your key team leader are really struggling with estimating the overall cost of the project. The most probable cause for this estimating difficulty can be attributed to:A. Initial poor scope definitionB. Lack of required resourcesC. Insufficient funds D. Problems with the overall schedule

Which of the following is the least accurate effort estimate? An effort estimate based on assigned resourcesAn effort estimate based on expertise of individualAn effort estimate based on past projectsAn effort estimate for a new process

Using a rule of thumb approach to come up with a set of estimates for a project can best be described as which decision making model?Question 80AnswerSelect one:a.Simons decision making modelb.What if Analysisc.Trial and errord.Heuristicse.Simulation

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.