Once the network diagram is complete, how many activities or milestones will not have both a predecessor and a successor? A. 1 B. 1 in each phase C. As many as necessary D. 2 in the entire network
Question
Once the network diagram is complete, how many activities or milestones will not have both a predecessor and a successor? A. 1 B. 1 in each phase C. As many as necessary D. 2 in the entire network
Solution
The answer is D. 2 in the entire network. In a network diagram, the first activity or milestone (start point) will not have a predecessor and the last activity or milestone (end point) will not have a successor. Therefore, there will be 2 activities or milestones in the entire network that will not have both a predecessor and a successor.
Similar Questions
Create Network Diagram (2.5pts) A. Use Ms Project to draw a network from the following information. ID Predecessor A None B A C B D B E C F C G D E F H G B. What type of activity is each of the following? Choose one of the following: neither burst nor merge, or burst, or merge. Activity A Activity B Activity C Activity D Activity E Activity F Activity G Activity H
Create Network Diagram (2.5pts) A. Use Ms Project to draw a network from the following information. ID Predecessor A None B A C B D B E C F C G D E F H G
The sequence of activity in network diagrams is shown by?a.Arrowsb.Nodesc.Circlesd.squares
In a project, a network diagram shows the ------------ relations of theinter related activities along with their corresponding activity times. deterministic and probabilistic precedence or succession union and intersection dummy and artificial
Question 5 (10 marks)Activities A to P are part of the set-up of a music festival. The network diagram below shows theseactivities and their completion time in days.G2 J5M4N2E5H2B3A5D4C3F4P3L3K7startfinish(a) Which activity must be on the critical path?(1 mark)A forward and backward scan has been completed on the network diagram below.5 50 03 4 8 813 1317 1715 1722 2219 2124 24G2J5M4N2E5H2B3A5D4C3F4P3L3K717 17startfinish(b) State the critical path(s) for the set-up of the music festival.(2 marks)page 11 of 23 PLEASE TURN OVER(c) Calculate the amount of slack time available for activity L