Knowee
Questions
Features
Study Tools

Solve the following problem by using the inverse of the matrix involved.An automobile factory produces two models, A and B. Model A requires 1 labour hour to paintand 30 minutes of labour to polish; model B requires 1 labour hour for each process. Duringeach hour that the assembly line is operating, there are 100 labour hours available for paintingand 80 labour hours for polishing. How many of each model can be produced each hour if allthe labour hours available are to be utilised? Round your answers to the nearest whole number.

Question

Solve the following problem by using the inverse of the matrix involved.An automobile factory produces two models, A and B. Model A requires 1 labour hour to paintand 30 minutes of labour to polish; model B requires 1 labour hour for each process. Duringeach hour that the assembly line is operating, there are 100 labour hours available for paintingand 80 labour hours for polishing. How many of each model can be produced each hour if allthe labour hours available are to be utilised? Round your answers to the nearest whole number.

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we will use the concept of matrix inversion.

First, we need to represent the problem as a system of linear equations.

Let's denote the number of Model A cars produced as x and the number of Model B cars as y.

From the problem, we know that:

1x + 1y = 100 (This represents the labour hours for painting)

0.5x + 1y = 80 (This represents the labour hours for polishing)

We can represent this system as a matrix equation AX = B, where A is the matrix of coefficients, X is the column vector (x, y), and B is the column vector on the right side of the equation.

So, A = [[1, 1], [0.5, 1]], X = [[x], [y]], and B = [[100], [80]].

To find X, we need to multiply both sides of the equation by the inverse of A. The inverse of a 2x2 matrix [[a, b], [c, d]] is (1/(ad-bc))*[[d, -b], [-c, a]].

The determinant of A (ad-bc) is (11 - 10.5) = 0.5. So, the inverse of A is (1/0.5)*[[1, -1], [-0.5, 1]] = [[2, -2], [-1, 2]].

Multiplying the inverse of A by B gives us X = [[2, -2], [-1, 2]] * [[100], [80]] = [[0], [60]].

So, the factory can produce 0 of Model A cars and 60 of Model B cars per hour to fully utilise the available labour hours. Since we can't produce a fraction of a car, and we need to round to the nearest whole number, the factory can't produce any Model A cars and can produce 60 Model B cars per hour.

This problem has been solved

Similar Questions

A manufacturer produces two products A and B that are processed on two machines I and II before completion. Machine I can process either 25 units of product A or 10 units of product B per hour. Machine II can process 40 of product B or 20 units of product A per hour.Using matrices determine the following:(i) Monthly output of products A and B if machines I and II operate for 8 and 7 hours per day respectively in a 6-day working week with 4 weeks in a month.mission0000(ii) Per unit cost of production if the cost of operating per hour on two machines is 25,000 and 30,000 respectively.(iii) Total cost of production.

An agriculture equipment manufacturer has a sub-assembly production line where eight steps or tasks must be performed (outlined in the table below with all relevant information). Daily demand (required output rate) is 54 units and there are 960 minutes available each day to meet this production quota.Task     Req'd Time (in minutes)     Predecessor A 9 NoneB 5 AC 5 BD 7 BE 13 CF 3 CG 7 D, E, FH 3 G What is the total time (in minutes) for this production line?   What is the takt time (in minutes) for this production line? (Round your answer to a one decimal place.)   What is the theoretical minimum number of workstations required for this production line? (Round up your answer to the nearest whole number.)   Given your task assignments to workstations, what is the actual number of workstations required?   What is the cycle time (in minutes) for this production line?   What is the overall efficiency for this production line? (Write your answer as a percentage, and display your answer to two decimal places.)   %

Ten basic tasks must be performed on an assembly line to manufacture a product. The demand forthe product is 60 units per day and the line is available 8 hours per day. The time to perform eachtask and the immediate predecessors are shown below:a) Draw a precedence diagram of this operation. b) Compute the cycle time for this operation. c)What is the theoretical minimum number of workstations? d) Assign tasks to workstations tominimize idle time. e) What is the idle time of the process? f ) What is the efficiency of theassembly line, given your answer in (d)?

55 trained workers and 33 untrained workers can assemble 1818 robots per hour. 66 trained workers and 44 untrained workers can assemble 2222 robots per hour. The number of robots that a trained worker can assemble in 11 hour is 𝑡t and the number that an untrained worker can assemble in the same time is 𝑢u. The matrix is equivalent to:

9. Three people A, B, and C are working in a factory. A and B working together can finish a task in 18 days whereas B and C working together can do the same task in 24 days and A and C working together can do it in 36 days. In how many days will A, B, and C finish the task working together ?*16201525

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.