General concrete knowledge:   HE stands for High Early Strength Cement.  Select all of the correct statements regarding HE cement.  Marks are awarded for each correct selection, but are deducted for incorrect selections.  Total marks awarded for this question will not be less than zero. a. Strength achieved at 7 days by concrete using HE cement is lower than the strength achieved at 7 days when using GP cement. b. Concrete made with HE cement is suitable for use in situations where it is beneficial to strip formwork early. c. Concrete made with HE cement produces greater heat of hydration than GP cement. d. Concrete made with HE cement produces less heat of hydration than GP cement. e. Concrete made with HE cement is suitable for use in thick concrete elements. f. Concrete made with HE cement is suitable for use in situations where there are low ambient temperatures (eg:  colder climates, early morning pours etc.) g. Strength achieved at 7 days by concrete using HE cement is higher than the strength achieved at 7 days when using GP cement.

Question

General concrete knowledge:   HE stands for High Early Strength Cement.  Select all of the correct statements regarding HE cement.  Marks are awarded for each correct selection, but are deducted for incorrect selections.  Total marks awarded for this question will not be less than zero. a. Strength achieved at 7 days by concrete using HE cement is lower than the strength achieved at 7 days when using GP cement. b. Concrete made with HE cement is suitable for use in situations where it is beneficial to strip formwork early. c. Concrete made with HE cement produces greater heat of hydration than GP cement. d. Concrete made with HE cement produces less heat of hydration than GP cement. e. Concrete made with HE cement is suitable for use in thick concrete elements. f. Concrete made with HE cement is suitable for use in situations where there are low ambient temperatures (eg:  colder climates, early morning pours etc.) g. Strength achieved at 7 days by concrete using HE cement is higher than the strength achieved at 7 days when using GP cement.

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct statements regarding High Early Strength Cement (HE cement) are:

b. Concrete made with HE cement is suitable for use in situations where it is beneficial to strip formwork early. This is because HE cement gains strength faster than General Purpose (GP) cement, allowing for the formwork to be removed sooner.

c. Concrete made with HE cement produces greater heat of hydration than GP cement. The heat of hydration is the heat produced when water and cement react. High early strength cement produces more heat faster than GP cement because it reacts faster.

f. Concrete made with HE cement is suitable for use in situations where there are low ambient temperatures (eg: colder climates, early morning pours etc.) The faster reaction time of HE cement can help counteract the slower curing times in cold weather.

g. Strength achieved at 7 days by concrete using HE cement is higher than the strength achieved at 7 days when using GP cement. This is the defining characteristic of HE cement - it gains strength faster than GP cement.

The incorrect statements are:

a. Strength achieved at 7 days by concrete using HE cement is lower than the strength achieved at 7 days when using GP cement. This is incorrect because HE cement is specifically designed to gain strength faster than GP cement.

d. Concrete made with HE cement produces less heat of hydration than GP cement. This is incorrect because the faster reaction of HE cement actually produces more heat.

e. Concrete made with HE cement is suitable for use in thick concrete elements. This is incorrect because the greater heat of hydration produced by HE cement can lead to thermal cracking in thick elements.

This problem has been solved

Similar Questions

General concrete knowledge:  Select all of the statements below that accurately describe curing of cement.  Marks are awarded for each correct selection, but are deducted for incorrect selections.  Total marks awarded for this question will not be less than zero. a. Concrete doesn't start to achieve strength gain until it dries out, so should be kept dry.  Curing methods are designed to keep out any excess moisture from the surrounding environment. b. Concrete has achieved its full strength as soon as it has set (hardened). c. Curing methods are designed to keep the concrete moist, allowing the hydration reactions to continue. d. Concrete reaches it's maximum strength at 28 days. e. Concrete continues to gain strength over its lifetime, but at a reducing rate. f. Different types of curing methods have no impact on the rate of strength gain for concrete. g. A higher ultimate strength can be obtained with a longer curing time. h. After 28 days, concrete has achieved most (but not all) of it's strength.

The diagrams below show the stages and equipment used in the cement-making process, and how cement is used to produce concrete for building purposes.Summarize the information by selecting and reporting the main features and make comparisons where relevant.

Which of the following dental cements is used as a luting and base cement and is high in strength?

Compressive Strength of Concrete

What is the particle density of concrete?Group of answer choices2.41.51.02.64

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.