In the Program Evaluation and Review Technique (PERT), the ________ determines the minimum amount of time in which a process can be completed.Multiple Choicesequencepredecessor eventjob scopecritical path
Question
In the Program Evaluation and Review Technique (PERT), the ________ determines the minimum amount of time in which a process can be completed.Multiple Choicesequencepredecessor eventjob scopecritical path
Solution
The correct answer is "critical path". This is because in the Program Evaluation and Review Technique (PERT), the critical path determines the minimum amount of time in which a process can be completed. It is the longest sequence of tasks in a project plan which must be completed on time for the project to complete on due date. Any delay in any task in the critical path directly impacts the project completion date.
Similar Questions
The PERT in project management means program evaluation and _____ technique.
What is the full form of PERT?a.Project evaluation and review techniqueb.Programme evaluation and review technique.c.Problem evaluation and review techniqued.Project evaluation and revision technique
What is an accurate difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM)?Group of answer choicesPERT uses different duration estimates whereas CPM uses one specific duration estimate.CPM involves more work than PERT because it requires several duration estimates.CPM addresses the risk associated with duration estimates whereas PERT does not.Unlike CPM, PERT estimates only when there is no risk of uncertainty.
PERT is a three time estimate and gives more weightage toQuestion 3Answera.Optimistic timeb.Most likely timec.Pessimistic timed.Expected time
PERT is suitable for _____________ project schedules.a.Optimizingb.Minimisingc.Maximizationd.None of the given options