X is four times as efficient as Y in respect of doing a particular work. Working together they complete the work in 16 days. In how many days y working alone will be able to half the work?

Question

X is four times as efficient as Y in respect of doing a particular work. Working together they complete the work in 16 days. In how many days y working alone will be able to half the work?

🧐 Not the exact question you are looking for?Go ask a question

Solution

Step 1: Understand the problem

The problem states that X is four times as efficient as Y. This means that if Y does 1 unit of work, X does 4 units of work.

Step 2: Calculate the total work done

When X and Y work together, they complete the work in 16 days. This means that in one day, they do 1/16 of the work.

Step 3: Calculate the work done by Y in one day

Since X is four times as efficient as Y, the work done by X and Y together in one day is 5 units (4 units by X and 1 unit by Y). So, 1/16 of the total work is equal to 5 units.

Step 4: Calculate the work done by Y alone in one day

If 5 units of work is equal to 1/16 of the total work, then 1 unit of work (which is what Y does in one day) is equal to 1/16 divided by 5, which is 1/80 of the total work.

Step 5: Calculate the time taken by Y to do half the work

If Y does 1/80 of the work in one day, then to do half the work (which is 1/2), Y will take 80 times 1/2, which is 40 days.

So, Y alone will be able to do half the work in 40 days.

This problem has been solved

Similar Questions

If A is 25% as efficient as B and can complete a certain work taking 15 days more than the time taken by B, in how many days will both A and B together complete the work?4 days5 days7 days10 days

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him until the completion of the work. How long did the work last?

6 persons working 5 hours a day can complete a work in 16 days .how many days will 4 persons wil take to complete the same work if each 6 hours a day​

X is twice as good a workman as Y and together they finish a piece of work in 18 days. In how manydays will X alone finish the work?26272528

A can complete a work in 18 days, while B can complete it in 12 days. B worked on it for 4 days. How long will A take to complete the remaining work?(1 Point)16 days12 days14 days10 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.