A RACI matrix tracks and assigns responsibilities to team members. Which of these items is NOT a part of the RACI matrix? Select an answer:ResponsibleInformedConsultedApproval

Question

A RACI matrix tracks and assigns responsibilities to team members. Which of these items is NOT a part of the RACI matrix? Select an answer:ResponsibleInformedConsultedApproval

🧐 Not the exact question you are looking for?Go ask a question

Solution

The item that is NOT a part of the RACI matrix is "Approval". The RACI matrix includes Responsible, Informed, and Consulted.

Similar Questions

Mark the statement that is true about a RACI matrixa.In a RACI matrix, only one person should be marked with A - assigned as accountableb.A RACI matrix describes the flow of information of a team working on a projectc.In a RACI matrix, only one person should be marked with R - assigned as responsibled.A RACI matrix is a tool helpful only for teams of above 8 members

In the RACI model, which role reviews the work to confirm it is complete?1 pointResponsibleAccountableConsultedInformed

A management team uses the RACI matrix to identify members involved in the change initiative. Which of the following describes the individual who oversees the entire change project?Selected answer will be automatically saved. For keyboard navigation, press up/down arrow keys to select an answer.aAccountablebResponsiblecConsulteddInformed

You assign someone as consulted in a RACI chart. What is their expected role in the project?1 pointTo ensure all the work gets doneTo complete the tasks in the projectTo know the final decision on the projectTo give feedback to the team

Which of the following individuals listed in the RACI performs the project work? ConsultedAccountableResponsibleInformed