answeredMarked out of 1.00Flag questionQuestion textThe decision to request an increase the resources for a project is the responsibility of the:a.Director of project managementb.Customerc.Functional managerd.Project manager
Question
answeredMarked out of 1.00Flag questionQuestion textThe decision to request an increase the resources for a project is the responsibility of the:a.Director of project managementb.Customerc.Functional managerd.Project manager
Solution
The decision to request an increase in resources for a project is typically the responsibility of the:
d. Project Manager
The Project Manager is usually the one who has the most intimate understanding of the project's needs and is therefore best equipped to make a case for additional resources. They are responsible for managing all aspects of the project, including resource allocation. If they determine that more resources are needed to complete the project successfully, they would be the ones to request an increase.
Similar Questions
Which of the following statements best describes the project manager's responsibilities in relation to scope change managementGroup of answer choicesThe project manager is responsible for relaying all change requests to a change control board and informing the customer about the board's decisions.The project manager is responsible for making all final decisions about the disposition of change requests and communicating those decisions to project stakeholders.The project manager is responsible for making sure all the client's change requests are carried out promptly.The project manager is responsible for identifying and documenting potential changes, assessing their impact on the project, providing that assessment to the change control board, documenting the decisions, and communicating them to project stakeholders.
For resource constrained project, the duration of the project might have to be increased in order to improve resource utilization.Group of answer choicesTrueFalse
During the resource levelling process, it is not important to maintain the logical relationship of project activities. Group of answer choicesTrueFalse
What is resource leveling in project management
When managers make decisions about resources such as funding, equipment, human labor, and office or production space, what role are they filling?a.)Allocatorb.)Equipment managerc.)Production space managerd.)Figurehead