Given the following information, calculate the direct labor price variance. Actual production in units17,000Standard labor cost per unit1/2 hour @ $20 per hourActual cost for labor$216,750 for 12,750 hoursMultiple choice question.$72,750 favorable$38,250 unfavorable$38,250 favorable$72,750 unfavorable
Question
Given the following information, calculate the direct labor price variance. Actual production in units17,000Standard labor cost per unit1/2 hour @ 216,750 for 12,750 hoursMultiple choice question.38,250 unfavorable72,750 unfavorable
Solution
To calculate the direct labor price variance, we need to follow these steps:
-
Calculate the Actual Labor Cost per Hour: This is done by dividing the total actual cost for labor by the total actual hours worked. So, 17 per hour.
-
Calculate the Standard Labor Cost per Hour: This is given in the problem as $20 per hour.
-
Calculate the Actual Hours Worked: This is given in the problem as 12,750 hours.
-
Calculate the Direct Labor Price Variance: This is done by subtracting the actual labor cost per hour from the standard labor cost per hour, and then multiplying the result by the actual hours worked. So, (17) * 12,750 hours = $38,250.
Since the actual labor cost per hour is less than the standard labor cost per hour, the variance is favorable.
So, the direct labor price variance is $38,250 favorable.
Similar Questions
Use the following data to find the direct labor rate variance if the company produced 3,500 units during the period. Direct labor standard (4 hours @ $12/hour) $ 48 per unitActual hours worked 12,250 Actual rate per hour $ 12.50 Multiple Choice$21,000 favorable.$6,125 unfavorable.$7,000 unfavorable.$14,875 favorable.$7,000 favorable.
Multiple Choice QuestionABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the direct labor variance.Multiple choice question.$14,400 F$14,400 U$24,400 U$24,400 F
A job was budgeted to require 2 hours of labor per unit at $11.00 per hour. The job consisted of 8,500 units and was completed in 16,000 hours at a total labor cost of $189,100. What is the total direct labor variance?
XYZ Company makes one product and has calculated the following amounts for direct labor: AH x AR = $84,000; AH x SR = $83,000; SH x SR = $85,000. Compute the direct labor cost variance.Multiple choice question.$2,000 F$1,000 U$2,000 U$1,000 F
Given the following information, calculate the direct material efficiency variance. Actual production in units17,000Standard cost for materials per unit$0.75 per pound × 3 poundsActual cost for materials$36,750 for 52,500 pounds Multiple choice question.$1,050 favorable$1,125 unfavorable$1,125 favorable$1,050 unfavorable
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.