During the number of efficiency truck calculations, if the production rate of excavating machine is higher than the production rate of hauling, which of the following scenario will be created in the site?
Question
During the number of efficiency truck calculations, if the production rate of excavating machine is higher than the production rate of hauling, which of the following scenario will be created in the site?
Solution
If the production rate of the excavating machine is higher than the production rate of hauling, it will create a scenario where the excavating machine will be waiting for the hauling machine to finish its task. This is because the excavating machine is producing more material than the hauling machine can handle. This can lead to inefficiencies on the site, as the excavating machine is not being used to its full capacity. It can also increase the cost of the project, as the excavating machine is still consuming fuel and requiring maintenance, even though it is not working at its full capacity. Therefore, it is important to balance the production rates of the excavating and hauling machines to ensure maximum efficiency on the site.
Similar Questions
What is producing output at the lowest possible total cost of production per unit called?Multiple choice question.Productive efficiencyAllocative efficiencyMarginal efficiencyMinimum efficiency
Kelsh Company uses a predetermined overhead rate based on machine hours to apply manufacturing overhead to jobs. The company has provided the following estimated costs for next year: Direct materials $10,000Direct labour 30,000Sales commissions 40,000Salary of production supervisor 20,000Indirect materials 4,000Advertising expenses 8,000Rent on factory equipment 10,000Kelsh estimates that 5,000 direct labour hours and 10,000 machine hours will be worked during the year. What will be the predetermined overhead rate per hour?
What is output per labor-hour?Multiple choice question.ProductivityCapital-intensiveLabor-intensiveA factor of production
A predetermined overhead application rate is established to apply manufacturing overhead to Blank______.Multiple choice question.finished goodsraw materialswork in processcost of goods sold
Which is the ratio of output work to input work?Multiple choice question.energyforceefficiencywork
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.