Select all that applyA project costs $2,000 and will be financed by shareholders. The expected value of the shareholders' interest is $1,000 without the project and $2,500 with the project. Why will the shareholders reject this project?Multiple select question.The bondholders would receive a $500 benefit at no cost to them.The shareholders will not invest because the project has a negative NPV.The shareholders would invest $2,000 but receive only a $1,500 benefit.The project is risky.
Question
Select all that applyA project costs 1,000 without the project and 500 benefit at no cost to them.The shareholders will not invest because the project has a negative NPV.The shareholders would invest 1,500 benefit.The project is risky.
Solution
The shareholders would reject this project for the following reasons:
-
The shareholders would invest 1,500 benefit. This means that the shareholders are making a net loss of 2000 - $1500) from this project. This is not a good investment for them as they are not getting a return on their investment.
-
The shareholders will not invest because the project has a negative NPV. NPV or Net Present Value is a measure of the profitability of a project. A negative NPV means that the project is not expected to generate a profit, but rather a loss. This is a major red flag for any investor.
The other options are not valid reasons for the shareholders to reject the project. The bondholders receiving a $500 benefit at no cost to them does not directly affect the shareholders' decision. The riskiness of the project is not specified, so we cannot assume that it is a reason for rejection.
Similar Questions
A Corporation must decide between two mutually exclusive projects. Both projects requirean initial spending of $100 million, and they generate cash ows that are independent of thegrowth of the economy.Project A has equal probability of four gross payos: $80 million, $100 million, $120 million,or $140 million.Project B has a 50/50 chance of paying either $90 million or $130 million.Assuming that the shareholders are all risk-averse, prove that they unanimously prefer projectB to project A.1
Select all that applyWhy are shareholders more keen on investing in high-risk projects during times of financial distress?Multiple select question.Bond covenants require shareholders to invest in high-risk projects during times of financial distress.The shareholders will lose no more than they've already lost.High-risk projects offer the potential for a higher return for shareholders.High-risk projects are likely to succeed during times of financial distress.
Suppose an investment has an initial capital cost of $500, an ongoing cost of $19.50 per year and an annual benefit of $160. If the project lasts for 5 years and the discount rate is 5%, the NPV is _______, the internal rate of return is ________ . If financing is required for this project and the financing rate is 15%, then the project should be ________.$108; 12.5%; rejected$103; 12.5%; rejected$108; 12.5%; accepted$103; 12.5%; accepted
If projects are mutually exclusive, then the NPV and the IRR may disagree on which project adds value to the shareholder's wealth.Select one:TrueFalse
An investor is considering three projects, A, B and C summarized in the table below. Investment cost Annual operating profit Project life (years)Project A -70000 17000 5Project B -90000 15000 8Project C -60000 13000 6Suppose the investor can borrow funds at an interest rate of 6%, by using the NPV rule with a 5% discount rate, he should choose project _____. When using the IRR rule, he should ____ this project.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.