Knowee
Questions
Features
Study Tools

Use the template to calculate the net cash flows, NPV and IRR of the projects.Net Cash FlowProject/Year 0 1 2 3Project A Net Cash FlowProject B Net Cash FlowNPV of A = IRR (A) =NPV of B = IRR (B) =Working TableDiscount rate = 10.0%Item/Year 0 1 2 3Capital Costs - A -100Capital Costs - B -100Operating Costs - A-20 -25 -30Operating Costs - B-15 -20 -25Gross Revenues - A 70 65 60Gross Revenues - B 45 65 75Net Revenues - ANet Revenues - B

Question

Use the template to calculate the net cash flows, NPV and IRR of the projects.Net Cash FlowProject/Year 0 1 2 3Project A Net Cash FlowProject B Net Cash FlowNPV of A = IRR (A) =NPV of B = IRR (B) =Working TableDiscount rate = 10.0%Item/Year 0 1 2 3Capital Costs - A -100Capital Costs - B -100Operating Costs - A-20 -25 -30Operating Costs - B-15 -20 -25Gross Revenues - A 70 65 60Gross Revenues - B 45 65 75Net Revenues - ANet Revenues - B

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

First, we need to calculate the net cash flows for each project for each year.

Net cash flow is calculated as Gross Revenues - Operating Costs.

For Project A: Year 1: 70 - 20 = 50 Year 2: 65 - 25 = 40 Year 3: 60 - 30 = 30

For Project B: Year 1: 45 - 15 = 30 Year 2: 65 - 20 = 45 Year 3: 75 - 25 = 50

So, the net cash flows for the projects are:

Project A: -100, 50, 40, 30 Project B: -100, 30, 45, 50

Next, we calculate the NPV (Net Present Value) for each project. The formula for NPV is:

NPV = ∑ [Cash inflow for year n / (1 + discount rate)^n] - Initial investment

For Project A: NPV = [50 / (1 + 0.1)^1] + [40 / (1 + 0.1)^2] + [30 / (1 + 0.1)^3] - 100 NPV = 45.45 + 33.06 + 22.52 - 100 NPV = 1.03

For Project B: NPV = [30 / (1 + 0.1)^1] + [45 / (1 + 0.1)^2] + [50 / (1 + 0.1)^3] - 100 NPV = 27.27 + 37.19 + 37.69 - 100 NPV = 2.15

Finally, we calculate the IRR (Internal Rate of Return) for each project. The IRR is the discount rate that makes the NPV of all cash flows (including the initial investment) from a project equal to zero.

Calculating IRR usually requires trial and error or financial calculator or software. However, in this case, we can see that the IRR for both projects would be slightly above the discount rate of 10% since the NPVs are positive at this discount rate.

So, the final results are:

Project A: Net Cash Flow: -100, 50, 40, 30 NPV: 1.03 IRR: >10%

Project B: Net Cash Flow: -100, 30, 45, 50 NPV: 2.15 IRR: >10%

This problem has been solved

Similar Questions

Using the method of your choice, calculate the Net Present Value of the following cash flows. Assume that the required return on this project is 15%  Project AInitial Cost -$ 150  Year 1 $ 175  Year 2 $ 100

There are two projects: project A and project B. Each of the project has the cost of Rs 100,000 and cost of capital for each project is 12 percent. The project's expected net cash flows are as follows: Year Project A Project B 0 Rs (100,000) Rs (100,000) 1 65,000 35,000 2 30,000 30,000 3 30,000 30,000 4 10,000 10,000 a. Calculate NPV for each project. Which project or projects should be accepted if they are independent? b. Calculate IRR for each project. Which project should be accepted if they are mutually exclusive?

Use the discount factor to find the NPV of both projects using the following table.Project/Year 0 1 2 3Project A Cash Flow -100 50 40 30Project B Cash Flow -100 30 45 50Discount factor (10%)Discounted Cash Flow of ADiscounted Cash Flow of BNPV of A (10%) =NPV of B (10%) =

Your boss the chief financial officer (CFO) asked you to analyse 3 different projects under consideration by the company's board. All projects require an initial investment and then provide a perpetuity of cash flows with zero growth. All are equally risky with the same 10% pa required return. All figures are rounded to 4 decimal places. The projects can all be accepted and funded, they're not mutually exclusive.The projects' initial costs and perpetual annual cash flows were provided by the engineering and marketing departments and are believed to be accurate. You calculated the NPV's and IRR's in bold, and made some conclusions about which projects to accept or reject (stated in answer option d). The CFO thanked you for your swift work, but said there's just one thing wrong with your calculations or conclusions, and asked you to fix it up before the table and conclusions are shown at the board meeting tomorrow.Projects with 10% pa required return  Initial cashflow at t=0 Perpetual annualcash flow from t=1 NPV IRR  ($m) ($m) ($m) (% pa)Project A -40 16 (a) 120 40Project B -1,200 80 -400 (b) 6.6667Project C -26,000 1,400 -12,000 (c) 6.698  Which one of the following calculations or conclusions is NOT correct?Question 7Select one:a.$120 million is project A's NPV.b.6.6667% pa is project B's IRR.c.6.698% pa is project C's IRR.d.Accept project A but reject projects B and C.

Discounted cash flows applicationsNet present Value calculations have a broad range of applications in finance.Calculate the NPV of the project based on the information below.Initial investment: $20,000Cash flow generated each year: $5,000Total period: 5 YearsDiscount rate: 6%

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.